Namaskar friends, welcome to session 23, in
our course on Operations Management. We are currently in the 5th week of our discussion
on this course on operations and we have discussed the basic aspects of the course, on Operation
Management till date. If you remember, just to have a brief revision
of what we have covered till today; we have covered the scopes objectives functions of
operations management in week 1. Then, in week 2, we have covered product design
and development. In week 3, we have covered the sales forecasting
aspects. In week 4, we have covered the plant location
aspect and in week 5, we are covering the plant layout. So, if you see we are trying to develop an
operation or an industry in which we are going to produce something tangible. So, starting from the fundamental aspects
of operations management; we have moved towards what we must produce, although we have limited
time to discuss product design and development. It can be studied as a full-fledged course
of 40 lectures. But we try to cover that we need to focus
on developing a new product, why? And what are the basic nuances related to
product design and development? That we have covered in one session. Then, we focused on how much products we must
make in our session or in our week on sales forecasting. Then, we thought that yes; we have an idea,
what we want to produce? We know how much we need to produce? We focused our attention on where we must
produce and produce and you know that we have already covered in week 4, the factors affecting
the location of the plant and where like in which state, in which district, in which part
of the country, we must set up our operations. So, that we have already studied in our week
4. Now we are in week 5, in which we are covering
that once we have decided where we are going to produce our product, where we are going
to operate; we are trying to set up our plant in the most effective manner. We are trying to understand that, what are
the strategic types of layouts or what are the basic type of layout which are being followed
by industry? If you see, I think all of us travel and go
to different hotels and stay in different hotels, most of the good hotels you will see
that a layout of the room is more or less consistent. Now, why most of the hotels have similar kind
of layout of the bed and the television as well as a table, chair, the washroom, the
dressing room; while a specific type of layout is there. Because the things have been or the parameters
have been optimized over a period of years and the optimized results have now become
standard. Similarly, the layouts that are followed in
industry are more or less standardized, why? Because all optimization related to movement
of material, movement of men, inspections, supervision all these things have been optimized
that which type of layout is good for which type of industry. We have seen in our course, in this week only
we have covered in the very first session the fundamental aspects of layout and what
are the important factors governing layout? And, we have seen that the type of industry,
the type of product we are producing, the volume of production all these aspects are
very important related to the selection of a layout. Now, we are trying to understand that what
are the various types of layouts? What are the important factors related to
the layout? And I have highlighted I have emphasized. Again, I am emphasizing today that layouts
of an industry are an important aspect and they are important from the examination point
of view; in most of the question papers related to the industrial engineering or operations
management, you will definitely find a question related to the layouts or the type of layout. So, that is important even from the examination
point of view. So, we are trying to understand that what
are the various types of layouts being followed by the industry and today’s session we will
try to emphasize; we have already seen briefly that what are the factors influencing the
plant layout. Today we will slightly carry forward our discussion
and try to highlight each and every point which affects the selection or a type of layout. So factors influencing the plant layout is
the topic of our discussion today and we will be winding up the discussion on week 5 emphasizing
on all the aspects related to plant layout or factory layout. So, let us start the discussion for today
and today, we will try to cover that what are the important factors related to plant
layout? Now one of the most important factor which
we have already covered in our discussion during week 2, is Product related to which
we are doing the manufacturing or the Product for which we are doing the manufacturing activity. Now the type of product will also influence
the type of layout that we are going to follow; examples are given on your screen. So, the Type of product whether it is heavy
or light product, big or small product, liquid or solid in nature will affect the type of
layout that we are going to select. First example is, for uniform type of products,
product layout is suitable. Now, I think it must have been clear to all
of you that what is the product type of layout? We also call it as a line type of layout in
which the product that is being produced or manufactured follow a specific sequence of
operations. So, product type of layout is usually followed
for uniform type of products. Example, I think if it would have been a regular
class I would have been more than happy to ask questions from the students that give
me at least 3 examples, where this type of products are being produced or where product
type of layout is being used. But here I am trying to answer the question
that we can use this type of for layout in automobile industry; where, the assembly of
car or motorcycle is taking place. So, that can be one example; where, uniform
type of product, all cars produced are of same type. They are of same color or they can be of different
color also, but the type of car that is being produced will remain same or uniform. Similarly, we can take an example of a line
type of layout in FMCG goods also. Suppose, biscuits are being produced and 1
dedicated line is for a specific type of biscuit. So, there will be sequence that will be followed
and a complete sequence will give you a final product. So, that can be another example of a product
type of layout where, same product is being produced. Then, the next example is for customized product. Customized product means that it is the product
is customized to the needs requirements, specifications of the customer which means that as the customer
is changing, your product design is getting modified and for a variety of product designs,
our uniform or may be a line type of layout may not be suitable. Therefore, we will go for a process or a functional
type of layout where, you remember that there are different departments different sections. For example, we have seen there can be a drilling
section; there can be a milling section; there can be a grinding section having grinding
machines may be 8 to 10 type of grinding machines, within grinding also there can be different
types of grinders like bench grinder, there can be a cylindrical grinding machine, there
can be center less grinding machine; different types of grinding machines can be there. But that will be within the grinding section
only. So, that type of layout can be used, where
you have a frequent design changes in the product or the customized products are being
produced. For very bulky products, we can go for fixed
position type of layout. As we have seen in an example, where an Aircraft
was being manufactured. So, when you want to manufacture a bulky big
aircraft or a very big ship, in that case we will use a fixed position type of layout. Where, the product will remain at its position,
but the machine and men will move to that product to perform the specific operations
in order to ensure the complete assembly of the product. So, these are the important topics related
to the product or important factors related to the product that will influence the selection
of our layout. Similarly, the sales and demand also influence
the plant layout. Moreover, the volume and quality of product
are important factors to how that suppose, the quality criteria; quality is an important
criteria. We have to see that whether we are going to
go for an online quality control or we are going to do the quality control after the
product has been produced or we are going to check the quality during the line at 3
specific locations. So, depending upon the quality that we want
to ensure or the quality control policy that the company wants to frame; they will decide
that what type of layout should be used by the industry. Because these qualities control personnel,
quality control equipment also has to be integrated within the layout only. Some companies may have a policy that first
they will make the product and then, the product will go to a specific quality control section;
where, the quality personnel will ensure that whether the product being manufactured is
meeting the specifications or not. So, that can have a different; maybe thought
related to the layout because you have a separate section of quality control. But in some cases the quality personnel may
be deputed on the line itself in order to ensure the intermittent or inter level maybe
during the line. They will be checking whether the product
is meeting the specifications or not and depending on that the layout will be influenced. The volume of production also; in case of
an aircraft, the volume of production may not be that much. Because the product will be produced as per
order and the delivery dates will be negotiated and decided dependent upon or depending upon
the production facility of the company. So, the production may not be too large in
number. So, therefore, we may easily go for fixed
position type of layout; whereas, in case of cars or motorcycle that demand may be large. So, volume of production required is also
large and line type of layout where every minute every 5 minutes we are producing one
vehicle that type of layout will be more suitable; because it is mass or continuous type of manufacturing
that is desirable in case of automobile industry; where, the demand is large. And therefore, the layout which can sustain,
which can produce that kind of products to satisfy that demand will be more suitable
in an automobile industry. So, the volume, the quality, the sales, the
demand all these parameters and all these parameters are related to the product. So, product that we are producing is the first
influencing factor, influencing our decision regarding the selection of a particular type
of layout. So, first thing you should remember regarding
the plant layout is plant layout starts with p and product also starts with p. So, p and p we should remember that for plant
layout product is one of the foremost parameters that must be considered and related to the
product, volume of production, demand in the market, quality of the product that we want
to ensure size of the product whether it is large, medium; variety of products that we
are producing all these are other parameters may be secondary parameters product overall
may be primary and then related parameters are secondary. All these parameters will affect our decision
related to the selection of the layout. But this is not the only parameter; there
will be a series of parameters or factors which will influence our decision. So, let us take the other parameters also. The other factor is Materials. The types of Raw Material whether it is solid,
liquid, gas, heavy, small or large. So, depending upon the type of material, we
are handling; we have to select our layout. For example, that we are having large sheets
of metal that we have to handle. So, definitely we will require a layout where,
we can have a place to handle all these big sheets. We may require to cut them using may be a
plasma arc welding process. Or plasma our cutting process. So, there we require that this machine wherever
we are locating this machine, there should be an appropriate place where we can keep
these big sheets. So, the size, the shape, the form may be whether
it is solid liquid or gas. So, all these will influence the selection
of our layout. Need for storage of different types of materials. As I have already told big materials may require
different types of storage space; small materials, very small materials may also require different
types of storage space. There may be materials as I know; we have
done a course on processing of polymers and polymer composites also. There are prepregs which have to be specifically
stored at minus 18 or minus 20 or minus 30 degree centigrade. Now the place where they are stored and the
place where they are being used; there should be minimum distance between these 2 places
and this will also affect the selection of our layout that what type of layout we must
follow. Because as soon as we take this material out
of that temperature where we are maintaining it, it will start the process of polymerization
and we want to use it as quickly as possible. And we have to place it on our mold. So, that is one specific requirement and one
example I am sharing with you that the need for storage of the different types of material
will also influence our decision related to the layout. The movement and placement of different types
of materials during processing; so, maybe that is also important the working process
and the other parameters related to the movement of the materials will also influence the selection
of our layout movement and placement of different types of materials during processing. For example, let us take an extreme case,
there is no movement of the material as in case of very bulky and large sized product. So, definitely we will say this is large size
product movement is difficult. So, let us go for a fixed position type of
layout only. And in line type of layout the movement is
linear, sequential operations are being performed; we will say the movement is in one direction
only. The raw material is entering the company or
the factory from one end and the product is coming out from the other end. So, there is a sequential operation. So, let us have a line or a product type of
layout. So, the movement of material is also very
important. Then, maybe the tertiary parameters like manpower. . The Availability of the workforce, Skills
and Experience of the workforce Position of an employee whether the employee is stationery
or the employees moving, Employee safety. So, all these are also parameters which will
help us to take our decision related to the selection of the layout. Then the factory building; the building that
we are going to erect or that we are going to construct for manufacturing facility is
going to influence the type of our layout. The nature and size of the building determines
the floor space available for the layout. So, depending upon the floor space available,
we will try to ensure the maximum utilization of space. So, that we are able to effectively and efficiently
convert the raw materials into the final product. So, in building whatever space is available,
the type of building we have whether let us take an example that we have a single floor
building only; maybe it is a ground floor only. So, we have to see that where which facility
must be located? What type of layout we must follow? Whether we should go for a compartmentalized
or section wise type of layout or let us bring the raw material and let us have a sequence
of operations and let us push out the final product from the other end. So, depending upon the building and the space
required or the space available sorry, we will select our layout. Suppose, we have double storey, triple storey
building we will try to use the elevation also, the floors also and we will see that
what we can do on the ground floor; may be the heavy equipment can be placed on the ground
floor and the office space can be on the first floor or the quality control department can
be on the first floor and the offices can be on the second floor. Now depending upon the type of building, we
will see that we will decide that what type of layout we are going to use. And we will see in our subsequent session
on flow of material or material flow lines and there we will see that we can have a flow
on the may be ground floor only and we can have vertical flow also; maybe we can classify
it as horizontal flow lines; may be on one floor only. The material is moving and getting converted
into final product and moving out and we can a vertical flow also where the material is
moving across different floors of the building. And then it is finally, getting converted
into the final product and going out. So, the type of building will also influence
our decision related to the type of layout that are going to follow. So, while designing the factory building,
following requirements must be kept in mind like the air conditioning, dust control, humidity
control and these are may be very textual or theoretical type of guidelines. In the current scenario people are focusing
on or the scientists, engineers are focusing on green buildings, natural ventilation, use
of solar energy, use of the draft of air, making windmills, using windmills, using natural
energy. So when you are trying to develop a factory
building or trying to develop a building for creating a manufacturing facility, these are
not the only parameters in the current scenario in 2017 we have to focus on. So, many other things like the catchword can
be green buildings using the energy. Then, there can be the utilization of the
waste water that we are doing can be recycled, recycling of waste water, recycling of the
solid waste generated, recycling or the proper waste disposal are important parameters that
have to be considered when we are developing a factory building. So, that is maybe a additional information
not available in the textbooks, but as engineers we must be very very sensitive towards our
planet and the technology that we develop, we need to keep a focus on the planet that
how it is going to affect the environment. Because we have to leave this planet for our
children, for our grandchildren. So that, they can have a happy life, whenever
we are talking of doing some developing some location, developing some factory location
or some factory layout or a factory building; we must also consider that how this is going
to affect the environment. Whether it is going to have a positive impact
on the environment or whether it is going to have a negative impact on the environment. So, that type of analysis; there are experts
who carry this type of analysis and rate the buildings accordingly. So, whenever we are talking of a factory building,
a factory layout; we must also consider its influence on the environment. That is also important to all of us to understand. Then the Location is also important; Topography,
because sometimes you may not have a flat land space available with you there may be
a topological change. So, we need to see that how the layout should
be designed that that topology is well taken care of and taken advantage of, for example,
you may have a specific topology where gravity can be made use of for material handling that
can be taken advantage of shape and size of the plant will also influence Climatic conditions. For example, we are setting up a plant in
the hills where you need not have any requirement of air conditioning. So, there also we need not have an air conditioning
plant and it will affect the type of layout that we are using for manufacturing type of
a product or a particular product. Availability of water, raw material, power
will also influence our decision related to the location within the premises and Waste
disposal facility is also very very important. Suppose, we need to have a ESP for cooling
or for purifying the air, to reduce the air pollution. So, that is one thing; we may have an effluent
treatment plant. Suppose, we want to put alongside our factory
that will influence our layout that we need to push out the used water in a direction
where, we have our effluent treatment plant. So, similarly, we have to plan our layout
in such a way there are the effluents are treated properly before being disposed into
the; maybe a river or a drain whatever is being used by the industry for its effluent
treatment. Because once it is treated you can just relieve
it because there are guidelines that what type of effluent you can leave in that drain
or into a river. So, there are guidelines if you are able to
treat your effluent to that level, you can release it in the drain. How it will influence? As I have already explained wherever you set
your treatment plant your inside layout will have to be modified accordingly. So, that the output goes or the waste goes
towards the plant. So, definitely it will influence the layout
in a specific or a particular manner. So, waste disposal facility, availability
of water, air, raw material and power that will also and influence your decision that
how the layout has to be planned. Now some of you may be wondering that there
are so many parameters, how we will be able to incorporate each and every parameter in
the selection of a layout? I understand that yes, it is a challenging
task; but in the very beginning of today’s session if you have tried to read between
the lines, I have emphasized that researchers, scientist industrialists, businessmen, business
wizards have already standardized few types of layout. They have optimized the types of layouts based
on all these factors that we are considering today. So, now, what we have to do we have to choose
from among these 4 or 5 specific types of layout which have already been optimized and
see that minor tweaking required in these layouts which will specifically customize
these layouts to our requirement. I think, I have been able to make myself absolutely
clear that we have a standard types of layouts which are available in the textbook. We have these factors which must be taken
into account while selecting a layout. Then, out of these 4 or 5 based on these parameters,
we can select 1 or 2 which can be best suited to our requirement. And then as per our requirement, we can do
the final customization of these standard layouts. So, location is also an important parameter
policies of management is also important. So, the policies of management related to
Volume of production, Size of the plant. Company maybe a medium or small scale industry. So, they know that, what is our capability? What is our strength? What type of production we are doing? So, that will decide on the size of the plant. Sales and marketing policies, purchasing policies;
Facilities to the employees, they want to create. Future targets, future expansion. So, all these parameters related to the decisions
or strategic policies of the management will also influence the type of layout. For example, the last point I want to emphasize
that is the future targets. Now the company feels that they are into a
niche market and maybe in the next 10 years, their volume of production is going to be
3-fold or 4-fold. Definitely they will require expansion. So, they need to see that what type of layout
they must follow; whether they should keep some space in the same plant for future expansion
or they should expand maybe in other areas or other zones of the country. So, all these policies of the management will
influence the type of layout that we are going to have. Similarly, the facilities they want to create
for their employees. Suppose, they want to have a residential campus
only; all employees have to stay in the premises on the of the organization. Then, specifically they have to create the
living facility, the buildings for insuring the flats and houses for the employees, the
recreational facilities for the employees. So, once that is decided by the organization. They have to decide the layout of the organization
in that manner only; that yes, within the layout facilities for residences also have
to be created. So, every parameter has to be taken into account
if we want to create a good layout a good working condition as well as a good living
condition for the employees of the organization so. So lastly, we can see that the Nature of manufacturing
process will also affect selection of the layout. Very quickly, we can classify the manufacturing
processes; I am a mechanical engineer at least we have 2, 3, 4 classifications possible for
the manufacturing processes. But today, we will try to classify the manufacturing
processes based on the type of layout that can be used for processing. For example, the first one, Synthetic process-
Under this process two or more materials are mixed to get a product. Example is also given-cement manufacturing. Analytical process- Under these method different
products are extracted from one material for example, extraction of oil from crude. So, we have Synthetic process, we have Analytical
process; we have Conditioning process. Under this process, the original raw material
is given the shape of different products and nothing is added to it. For example, jute is an important example. So, we are not adding anything, we are not
maybe removing much from the jute, but we are giving or we doing something with the
jute and making it into a tangible or a useable product. Similarly, Extractive process; this method
involves the extraction of a product from the original material by application of heat
or pressure. So, you can see synthetic process in the previous
slide; Analytical process; then, Conditioning process; then, extractive process. So, all these 4 types of processes, will maybe
focus on a specific type of layout only. So, they will also influence that which type
of layout is suitable for a specific type of process. Finally, we come to an important point which
we have already covered if you remember; we have seen the type of production systems in
our very first week, in our fundamental week related to Operations Management; in our introductory
week related to the Operations Management. So, in very first week, we have seen the type
of production system actually every week is interrelated, interweaved with the other week. So, the complete course will give you a thought
process that suppose we want to produce something, what are the different things that should
be covered that we should keep in mind. So, that we are able to bring good name to
the organization as well as good profit for the organization. These 3 things we have already covered. Plant layout is generally determined by taking
into consideration; the quantum of products to be produced and this we have already related
very quickly within a minute or 2; I will try to relate the 2 things. In job shop type of production all of you
know it is intermittent type of production, design changes are very frequent. So, we would like to go for a process or functional
type of layout. In batch production also we would like to
go for process or batch type of process or functional type of layout. In mass production we would like to go for
a product or a line type of layout. So, the type of production that’s we are
following or the type of product production system that we are following will also influence
the plant layout or the selection of the plant layout. In job shop and batch type of production,
the product changes the customized products are produced; when the product change is frequent
we would like to make it in different sections and the there can be a material flow line
which we will cover in the next session. So, depending upon the requirement or the
operations to be done on the product it will go to the specific departments and final product
will be produced. But in mass production, we will have a product
or a line type of layout in which the raw material will enter from one end of the organization. All operations will be performed in a sequence
and the final product will come out either from the same direction or from the opposite
direction depending upon the material flow lines or the material flow system that we
are following. So, we can see that the volume of production
is also an important aspect related to the selection of a layout. So, with this we come to the end of today’s
session and we have seen today that what are the various factors governing the factory
layout or the plant layout and how these factors influence our decision related to the selection
of the layout. Also you will appreciate that there are a
number of parameters which influence our selection and we have to judiciously take into account
these parameters for selecting a layout which will give us improved productivity as well
as efficient and effective manufacturing. So, in this week, we have today finished 3rd
session of our course. In the first 2 sessions, we have seen the
introductory aspects of the factory layout or the plant layout. We have seen the different types of layouts
and today, I think we have been able to properly appreciate the factors that are used for selection
of a layout. Also we have tried to emphasize with examples
that these parameters are really important in our decision related to the selection of
a layout for a particular manufacturing facility. Thank you.