HS2 Project Update, January 2024

Video Statistics and Information

Video
Captions Word Cloud
Reddit Comments
Captions
Hi, everybody. I'm Emma Head,  Chief Railway Officer at HS2,   bringing you our latest update on the work we've  been doing to build HS2. I'm delighted to be your   guide on this 140-mile whistle stop tour of the  construction progress we've made during 2023. HS2 is Britain's biggest build  and unprecedented in scale.  We're building more than 500 bridging  structures over and under the route,   more than 100 embankments and about 70  cuttings, the longest stretching 2.5 miles. As we start 2024, work is underway on over two  thirds of HS2’s viaducts and over half of our   bridges. Over 25 miles of tunnels have been  created by our giant tunnel boring machines. When the first HS2 services launch,  passengers will start their   journey at Old Oak Common Station in West  London, which will be the UK’s largest   new-build station and will be the line’s  temporary southern terminus. We’re into the   third year of permanent construction of this vast  station, and already we can see it taking shape.  Over half a million cubic metres of London clay  has been excavated to create the underground   station box, and construction of the  first of 14 new platforms is underway.  Once complete, Old Oak Common will integrate  into the existing network connecting HS2   with the Elizabeth line, the Heathrow  Express and the Great Western Main Line. To ensure trains can flow freely and on  time, as they leave Old Oak Common station,   they will pass through Victoria Road  Crossover Box. Over 130,000 tonnes of soil   has been removed to create the structure  – the same as 55 Olympic Swimming pools.  The huge, caterpillar shaped structure – 128m  in length and 25m deep – is approaching its   final stages of construction, and the western  section of the box has been handed over to our   tunnelling teams to become the launch chamber for  two huge tunnel boring machines, Emily and Anne. The two machines will start their  3.4-mile journeys in early 2024,   to dig the eastern section of Northolt Tunnel.  They will join our first two London TBMs,   Sushila and Caroline, who are already over one  year into constructing the western section of   the tunnel, with each machine having completed  over 2 miles of their 5-mile journeys so far. On the outskirts of West London,  construction of the Valley Viaduct   has passed its halfway mark on its journey  to become Britain's longest railway bridge.  Over 500 deck segments have been  manufactured and installed already.   All of the iconic V-shaped piers are complete  and our construction team is moving forwards,   assembling the 80 metre long spans that will  carry the railway across the lakes at 2.1 miles.  When complete, the Colne Valley Viaduct will set  a record as the longest rail bridge in the UK,   yet it will take just 40 seconds for passengers to  go across it in one of HS2’s bullet-style trains. Once across the viaduct, they will pass through  what will be the largest single project in our   Green Corridor programme – where our  teams have begun creating the first of   some 90 hectares of new chalk grassland using  chalk from our tunnelling activities. And then   head almost immediately into the 10-mile-long  Chiltern Tunnel, the longest tunnel on HS2.  Florence and Cecilia, our first pair  of HS2 tunnelling machines to launch,   are now over 90% of the way through  their journeys under the Chiltern hills,   and on track to complete their drives  and breakthrough at the north portal   of the Chiltern Tunnel in early 2024. And as the machines edge closer to that   finishing line, the expert team behind them  are installing the tunnel invert – which will   house the HS2 track – and constructing the  38 cross-passages that link the twin tunnels. As passengers exit the Chiltern tunnel heading  north, they will enter a network of cuttings,   embankments, viaducts and green tunnels, which  will support high-speed trains travelling up to   225mph across a broad range of landscapes,  to deliver a smooth, reliable journey.  Across 2023, we made huge progress on many of the  major structures that will carry HS2 trains into   the heart of the West Midlands and further north. The piers for Wendover Dean Viaduct are coming out   of the ground, as the team prepare to launch the  first sections of the low-carbon deck in 2024.  The first of 72 massive “Lego block”  beams have been lifted into place for   our pioneering Thame Valley Viaduct – the  first of its kind in the UK to have all   major elements manufactured off site. And the designs for Small Dean Viaduct   in Buckinghamshire, and Edgcote Viaduct  in Northamptonshire have been unveiled. As HS2 trains enter in Northamptonshire, they  will travel underground in two ‘green tunnels’.  Work on the 1.7 mile Greatworth Green Tunnel –  the longest cut-and-cover, or ‘green’, tunnel   on the HS2 route – started this year, with the  first of 5,410 segments being lifted into place.  Along with her sister tunnel – the 1.5 mile  Chipping Warden green tunnel – these tunnels   are built using an ‘M-shaped’ double arch design,  and, much like many of the viaducts on the route,   all major components are precast in a factory  offsite, before being assembled onsite.  Once complete, the tunnels will be covered  with earth and landscaped to a tailored design,   featuring thousands of native trees and shrubs.  Over 35 million cubic metres of material has been   excavated across the route to create below-ground  cuttings to date, using a fleet of machines,   which are carefully tracked and monitored using  an innovative, real-time reporting system.  Around 95% of material excavated is reused on  site to create our embankments, noise barriers   and landscaping. We are moving about 99% of  the material on HS2 land using a network of   temporary haul roads, to reduce traffic on public  roads and minimise impacts of local communities. As the route enters south Warwickshire,   we dip below ground again into  the Long Itchington Wood Tunnel.  The second drive of the twin-bore tunnel,  which takes HS2 under an ancient woodland,   was completed in March 2023 when TBM  Dorothy broke through at the south portal.  After that breakthrough, TBM Dorothy was  dismantled and transported to our Bromford   tunnelling site to be re-used to dig the tunnel  next door to the one we’re standing in right now. As we head north out of the tunnel, our trains  will travel along cuttings and embankments,   through a green tunnel at Burton Green  and under bridges – including the huge   5,600 tonne Kenilworth overbridge, which  was moved into place under the existing   Coventry to Leamington Line in July 2023. This was the third major bridge move delivered   over a two-week period, with structures  installed at Fulfen Wood near Lichfield   and at nearby Streethay, that will allow  HS2 to pass beneath existing railway lines,   on its route going north where it will  connect to the existing railway network. In Solihull, a huge amount of work has  been delivered over the past year to   prepare the area for construction  of the new HS2 Interchange Station,   including the removal of an existing bridge over  the M42 motorway, and work to improve and remodel   the local road and utility networks. This will create the space to build   the new eco-friendly HS2 station in the  heart of Solihull, which will be part   of a new public transport interchange  serving Solihull and the West Midlands. Heading north out of the station, our trains will  enter the Delta Junction – a triangular section of   the high-speed railway made up of nine viaducts,  embankments, and other bridging structures,   with around 10km of track crossing a  network of motorways, roads and rivers.  Across 2023 we saw the first piers for the  Water Orton and River Tame Viaducts completed,   and the first of over 2,700 individually cast   deck sections from our precast factory in  Kingsbury, have started to be installed. And as the railway sweeps west towards Birmingham,   we enter the Bromford Tunnel  where we’re standing today.  Over 1 kilometre of this tunnel has been completed  so far, and work is underway next door to prepare   a second tunnelling machine for launch in 2024. These machines will each dig around 3.5 miles of   tunnel, towards the western  portal at Washwood Heath. From Washwood Heath, where our depot and control  centre will be located, trains will head onto   a series of five connected viaducts that will  carry passengers right into central Birmingham.   We’ve made huge progress on those viaducts too,  with the first sections of the 300-metre-long   Curzon Viaduct deck poured, that will bring  high-speed trains into Birmingham's Curzon   Street Station. Foundation works will  begin at the 25-acre site in early 2024. I hope you’ve enjoyed this update  and seeing the scale of the works   that we’re delivering across over 350 active  sites between London and the West Midlands.  HS2 is the biggest and most ambitious  infrastructure project in the UK,   and we look forward to bringing  you more updates as we continue   to deliver Britain’s new high-speed railway. Thank you.
Info
Channel: HS2 Ltd
Views: 163,447
Rating: undefined out of 5
Keywords: high speed railway, united kingdom, HS2, tunnelling, train, engineering, construction, infrastructure, project, rail, railways, uk, civil engineering
Id: vy0KY4aKEmU
Channel Id: undefined
Length: 11min 4sec (664 seconds)
Published: Thu Jan 04 2024
Related Videos
Note
Please note that this website is currently a work in progress! Lots of interesting data and statistics to come.